[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> CC Construction Ltd v Mincione [2021] EWHC 2502 (TCC) (15 September 2021) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2021/2502.html Cite as: [2022] BLR 48, [2021] EWHC 2502 (TCC), [2021] TCLR 8, 198 Con LR 183 |
[New search] [Printable PDF version] [Help]
BUSINESS AND PROPERTY COURTS OF ENGLAND AND WALES
TECHNOLOGY AND CONSTRUCTION COURT (QBD)
7 Rolls Building, Fetter Lane, London, EC4A 1NL |
||
B e f o r e :
____________________
CC CONSTRUCTION LIMITED |
Claimant/Pt 8 Defendant |
|
- and - |
||
RAFFAELE MINCIONE |
Defendant/Pt 8 Claimant |
____________________
Gideon Shirazi (instructed by Charles Russell Speechlys LLP) for Raffaele Mincione
Hearing date: 13th July 2021
____________________
Crown Copyright ©
HH Judge Eyre QC:
Introduction.
The Factual Background.
"The design and construction of a new three storey single dwelling including three basement levels at the property shown edged red on the site plan annexed at Annex B."
"Any notice or other communication between the Employer … and the Contractor that is expressly referred to in the Agreement for these Conditions (including without limitation, each application, approval, consent, confirmation counter-notice, decision, instruction or other notification) shall be in writing."
".1 As from the due date for the final payment specified in clause 4.12.5 and in addition to the effect referred to in clause 4.12.6, the Final Statement or, as the case may be, the Employers Final Statement (`the relevant statement') shall, except as provided in clauses 1.8.2, 1.8.3 and 1.8.4 (and save in respect of fraud), have effect in any proceedings under or arising out of or in connection with this Contract (whether by adjudication, arbitration or legal proceedings) as:
…
.2 conclusive evidence that all and only such extensions of time, if any, as are due under clause 2.25 have been given: and
.3 conclusive evidence that the reimbursement of direct loss and/or expense, if any, to the Contractor pursuant to clause 4.20 is in final settlement of all and any claims which the Contractor has or may have arising out of the occurrence of any of the Relevant Matters whether such claim be for breach of contract, duty of care, statutory duty or otherwise.
.2 If adjudication, arbitration or other proceedings have been commenced by either Party before the due date for the final payment the relevant statement shall have effect as provided in clause 1.8.1 upon and from the earlier of either:
.1 the conclusion of such proceedings in which case the statement shall be subject to the terms of any decision, award or judgement in or any settlement of such proceedings; or
.2 the expiry of any period of 12 months from or after the submission of the statement, during which neither Party takes any further step in such proceedings…
.3 Subject to clause 4.12.6, if adjudication, arbitration or other proceedings are commenced by either Party on or after the due date for the final payment and not later than 28 days after the due date, the relevant statement shall have effect as conclusive evidence as provided in clause 1.8.1 save only in respect of the matters to which those proceedings relate.
.4 …"
"If at any time or times before the Practical Completion Statement or relevant Section Completion Statement the Employer wishes to take possession of any part or parts of the Works or a Section and the Contractor's consent has been obtained (which consent shall not be unreasonably delayed or withheld), then, notwithstanding anything expressed or implied elsewhere in this Contract, the Employer may take possession of such part or parts. The Contractor shall thereupon give the Employer notice identifying the part or parts taken into possession and giving the date when the Employer took possession ('the Relevant Part' and 'the Relevant Date' respectively)."
"When any defects, shrinkages or other faults in the Relevant Part which the Employer has required to be made good under clause 2.35 have been made good, he shall issue a notice to that effect provided that the Employer shall not be required to issue that notice earlier than the expiry of the Rectification Period for the Relevant Part."
"If any defects, shrinkages or other faults in the Works or a Section appear within the relevant Rectification Period due to any failure of the Contractor to comply with his obligations under this Contract:
.1 such defects, shrinkages and other faults shall be specified by the Employer in a schedule of defects which he shall deliver to the Contractor as an instruction not later than 14 days after the expiry of that Rectification Period; and
.2 notwithstanding clause 2.35.1, the Employer may whenever he considers it necessary issue instructions requiring any such defect, shrinkage or other fault to be made good, provided no instructions under this clause 2.35.2 shall be issued after delivery of a schedule of defects or more than 14 days after the expiry of the relevant Rectification Period.
Within a reasonable time after receipt of such schedule or instructions, the defects, shrinkages and other faults shall at no cost to the Employer made good by the Contractor unless the Employer shall otherwise instruct…."
"When the defects, shrinkages or other faults in the Works or a Section which the Employer has required to be made good under clause 2.35 have been made good, he shall issue a notice to that effect (a "Notice of Completion of Making Good") provided that the Employer shall not be required to issue any Notice of Completion of Making Good earlier than the expiry of the Rectification Period. That notice shall not be unreasonably delayed or withheld, and completion of that making good shall for the purposes of this Contract be deemed to have taken place on the date stated that notice."
"The Final Statement shall set out the adjustments to the Contract Sum to be made in accordance with clause 4.2 and shall state:
.1 the Contract Sum. as so adjusted; and
.2 the sum of amounts already paid by the Employer to the Contractor,
and the final payment shall be the difference (if any) between the two sums, which shall be shown as a balance due to the Contractor from the Employer or to the Employer from the Contractor, as the case may be. The Final Statement shall state the basis on which that amount has been calculated, including details of all such adjustments."
"The due date for the final payment shall be the date one month after whichever of the following occurs last:
.1 the end of the Rectification Period in respect of the Works or (where there are Sections) the last such period to expire;
.2 the date stated in the Notice of Completion of Making Good under clause 2.36 or (where there are Sections) in the last such notice to be issued; or
.3 the date of submission to the other Party of the Final Statement or, if issued first, the Employers Final Statement ("the relevant statement")."
"Except to the extent that prior to the due date for the final payment the Employer gives notice to the Contractor disputing anything in the Final Statement or the Contractor gives notice to the Employer disputing anything in the Employer's Final Statement, and subject to clause 1.8.2, the relevant statement shall upon the due date become conclusive as to the sum due under clause 4.12.2 and have the further effects stated in clause 1.8."
".7 The final date for payment shall be 28 days from the due date. Not later than 5 days after the due date, and notwithstanding any dispute regarding the relevant statement, the Party by whom the statement shows the final payment as payable ('the payer") shall give a Payment Notice to the other Party with the details specified in clause 4.10.1. Subject to any Pay Less Notice under clause 4.12.8 the payment to be made on or before the final date for payment shall be the sum stated in the Payment Notice or, if such notice is not given, the balance stated in the relevant statement.
.8 if the payer intends to pay less than the sum stated in the Payment Notice or, in default of such notice, less than the amount stated in the relevant statement, he shall not later than 5 days before the final date for payment give the other Party a Pay Less Notice in accordance with clause 4.10.2
.9 Where a Pay Less Notice is given, the payment to be made on or before the final date for payment shall not be less than the amount stated as due in the notice."
"Under the terms of the above Contract, I/We certify that in accordance with Clause 2.32 of the Contract, all defects, shrinkage is and/or other faults in the Works due to materials, goods or workmanship not in accordance with this Contract, which the Employer has required the Contractor to rectify, have been made good as of 7 February 2020."
"We are nearing the end of the Making Good Defects Period for the rear wall of Nr 57 Clabon Mews and it would be appreciated if the Final Statement could be agreed as soon as possible to tie in with the end of this period."
"I also refer to the Final Statement enclosed with your letter dated 5 October 2020.
In accordance with clause 4.12.6 I give notice that I dispute the content of the Final Statement in its entirety. In particular, and without limitation:…"
"On this basis alone (and, for the avoidance of doubt, I dispute all items in your Final Statement), the final payment would be a sum due from CC Construction to me.
In accordance with clause 4.12.7, I will provide a Payment Notice in due course."
"This Notice refers to the whole of the Works.
Under the terms of the above Contract, I/We certify that in accordance with Clause 2.36 of the Contract, all defects, shrinkages and or other faults in the Works due to materials, goods or workmanship not in accordance with this Contract, which the Employer has required the Contractor to rectify, have been made good as at 13 January 2021."
"The final date for payment is not 15 January 2021. As you are aware, clause 4.12.5 of the building contract provides that the due date for final payment is 28 days after the last of the following:
- The end of the Rectification Period
- The date stated in the Notice of Completion of Making good
- The date of submission of the final Statement.
The date stated in the Notice of Completion of Making Good was 13 January 2021. Therefore, neither the due date for the final date for payment has occurred."
"It is established law that an Adjudicator cannot open up a certificate considered to be conclusive, as such, once the due date has been determined, the Adjudicator will have no further power to open up the Final Statement. In respect of liquidated damages, I conclude that it is not a part of the dispute I have been asked to decide and therefore cannot be raised in set off in these circumstances."
The Procedural History.
The Issues.
The Due Date.
"If a term in a consumer contract … could have different meanings the meaning that is most favourable to the consumer is to prevail."
"When the defects, shrinkages or other faults in the Works or a Section which the Employer has required to be made good under clause 2.35 have been made good".
"half the Retention Percentage may be deducted from so much of the total amount as relates to work where the Works or relevant Section(s) have reached practical completion but in respect of which a Notice of Completion of Making Good under clause 2.36 has not been issued or relates to work in a Relevant Part where a notice under clause 2.32 has not been issued."
"It is my finding that a NMG is only issued under clause 2.36, where there are defects specified under clause 2.35, and if there are no defects, clause 4.12.5 cannot require the issue of a NMG for the purposes of calculating the due date for the final payment."
Was the Letter of 18th December 2020 effective to prevent the Final Statement becoming conclusive pursuant to Clause 4.12.6?
Should there be a Declaration as to the Effect of Clause 1.8.1?
"The Final Statement operates as conclusive evidence that (a) all and only such extensions of time, if any, as are due under clause 2.25 have been given and (b) the reimbursement of direct loss and/or expense, if any, to the Contractor pursuant to clause 4.20 is in final settlement of all and any claims which the Contractor has or may have arising out of the occurrence of any of the Relevant Matters, whether such claim be breach of contract, duty of care, statutory duty or otherwise. In consequence, the Contractor is not entitled to any extension of time beyond 11 July 2018, nor any additional sums beyond those certified under cl 4.20."
Did the Adjudicator have Jurisdiction to determine whether the Final Statement was conclusive?
"1. The word 'dispute' which occurs in many arbitration clauses and also in section 108 of the Housing Grants Act should be given its normal meaning. It does not have some special or unusual meaning conferred upon it by lawyers.
2. Despite the simple meaning of the word "dispute", there has been much litigation over the years as to whether or not disputes existed in particular situations. This litigation has not generated any hard-edged legal rules as to what is or is not a dispute. However, the accumulating judicial decisions have produced helpful guidance.
3. The mere fact that one party (whom I shall call "the claimant") notifies the other party (whom I shall call "the respondent") of a claim does not automatically and immediately give rise to a dispute. It is clear, both as a matter of language and from judicial decisions, that a dispute does not arise unless and until it emerges that the claim is not admitted.
4. The circumstances from which it may emerge that a claim is not admitted are Protean. For example, there may be an express rejection of the claim. There may be discussions between the parties from which objectively it is to be inferred that the claim is not admitted. The respondent may prevaricate, thus giving rise to the inference that he does not admit the claim. The respondent may simply remain silent for a period of time, thus giving rise to the same inference.
5. The period of time for which a respondent may remain silent before a dispute is to be inferred depends heavily upon the facts of the case and the contractual structure. Where the gist of the claim is well known and it is obviously controversial, a very short period of silence may suffice to give rise to this inference. Where the claim is notified to some agent of the respondent who has a legal duty to consider the claim independently and then give a considered response, a longer period of time may be required before it can be inferred that mere silence gives rise to a dispute.
6. If the claimant imposes upon the respondent a deadline for responding to the claim, that deadline does not have the automatic effect of curtailing what would otherwise be a reasonable time for responding. On the other hand, a stated deadline and the reasons for its imposition may be relevant factors when the court comes to consider what is a reasonable time for responding.
7. If the claim as presented by the claimant is so nebulous and ill-defined that the respondent cannot sensibly respond to it, neither silence by the respondent nor even an express non-admission is likely to give rise to a dispute for the purposes of arbitration or adjudication."
Was there a Material Breach of the Requirements of Natural Justice in the Adjudicator's Treatment of the Employer's Liquidated Damages Argument?
"22.1 The adjudicator must attempt to answer the question referred to him. The question may consist of a number of separate sub—issues. If the adjudicator has endeavoured generally to address those issues in order to answer the question then, whether right or wrong, his decision is enforceable: see Carillion v Devonport.
22.2. If the adjudicator fails to address the question referred to him because he has taken an erroneously restrictive view of his jurisdiction (and has, for example, failed even to consider the defence to the claim or some fundamental element of it), then that may make his decision unenforceable, either on grounds of jurisdiction or natural justice: see Ballast, Broadwell and Thermal Energy.
22.3. However, for that result to obtain, the adjudicator's failure must be deliberate. If there has simply been an inadvertent failure to consider one of a number of issues embraced by the single dispute that the adjudicator has to decide, then such a failure will not ordinarily render the decision unenforceable: see Bouygues and Amec v TWUL.
22.4. It goes without saying that any such failure must also be material: see Cantillon v Urvasco and CJP Builders Limited v William Verry Limited [2008] EWHC 2025 (TCC). In other words, the error must be shown to have had a potentially significant effect on the overall result of the adjudication: see Keir Regional Ltd v City and General (Holborn) Ltd [2006] EWHC 848 (TCC).
22.5. A factor which may be relevant to the court's consideration of this topic in any given case is whether or not the claiming party has brought about the adjudicator's error by a misguided attempt to seek a tactical advantage. That was plainly a factor which, in my view rightly, Judge Davies took into account in Quartzelec when finding against the claiming party."
25. It is not uncommon for adjudicators to decide the scope of their jurisdiction solely by reference to the words used in the notice of adjudication, without having regard to the necessary implications of those words: that was, for example, what went wrong in Broadwell. Adjudicators should be aware that the notice of adjudication will ordinarily be confined to the claim being advanced; it will rarely refer to the points that might be raised by way of a defence to that claim. But, subject to questions of withholding notices and the like, a responding party is entitled to defend himself against a claim for money due by reference to any legitimate available defence (including set-off), and thus such defences will ordinarily be encompassed within the notice of adjudication. "
26. As a result, an adjudicator should think very carefully before ruling out a defence merely because there was no mention of it in the claiming party's notice of adjudication. That is only common sense: it would be absurd if the claiming party could, through some devious bit of drafting, put beyond the scope of the adjudication the defending party's otherwise legitimate defence to the claim."
"Applying those legal principles to the circumstances that arise in this case, I make the following observations.
i) A referring party is entitled to define the dispute to be referred to adjudication by its notice of adjudication. In so defining it, the referring party is entitled to confine the dispute referred to specific parts of a wider dispute, such as the valuation of particular elements of work forming part of an application for interim payment.
ii) A responding party is not entitled to widen the scope of the adjudication by adding further disputes arising out of the underlying contract (without the consent of the other party). It is, of course, open to a responding party to commence separate adjudication proceedings in respect of other disputed matters.
iii) A responding party is entitled to raise any defences it considers properly arguable to rebut the claim made by the referring party. By so doing, the responding party is not widening the scope of the adjudication; it is engaging with and responding to the issues within the scope of the adjudication.
iv) Where the referring party seeks a declaration as to the valuation of specific elements of the works, it is not open to the responding party to seek a declaration as to the valuation of other elements of the works.
v) However, where the referring party seeks payment in respect of specific elements of the works, the responding party is entitled to rely on all available defences, including the valuation of other elements of the works, to establish that the referring party is not entitled to the payment claimed.
vi) It is a matter for the adjudicator to decide whether any defences put forward amount to a valid defence to the claim in law and on the facts.
vii) If the adjudicator asks the relevant question, it is irrelevant whether the answer arrived at is right or wrong. The decision will be enforced.
viii) If the adjudicator fails to consider whether the matters relied on by the responding party amount to a valid defence to the claim in law and on the facts, that may amount to a breach of the rules of natural justice.
ix) Not every failure to consider relevant points will amount to a breach of natural justice. The breach must be material and a finding of breach will only be made in plain and obvious cases.
x) If there is a breach of the rules of natural justice and such breach is material, the decision will not be enforced."
"The adjudicator correctly identified in paragraph 44 of the decision that the notice of adjudication set the boundaries of his jurisdiction. However, he failed to appreciate that what GSEL was claiming in the notice (at paragraph 31) was not only the true valuation of specific parts of Interim Applications 27 but also payment of the net sum considered due having regard to the sums already paid and applicable retention. The adjudicator was entitled to limit the declaratory relief to the issues of valuation identified by GSEL but determination of the claim for payment required him to consider all of the matters raised by Sudlows in support of its case that it was entitled to additional sums as part of the valuation. The adjudicator's failure to take into account Sudlows' defence based on its additional claims for loss and expense amounted to a breach of the rules of natural justice."
"… On the contrary he [the adjudicator] did consider it [the liquidated damages defence] and he concluded that, in the particular circumstances of this case, [the Employer] was not entitled to raise a claim for LADs in set-off against sums that he found due in respect of the Contract Sum as set out in the Final Statement".
"17. Mr Samuel Townend, who appeared for Urang, accepted that in principle the counterclaim could be deployed as a defence to all the claims, save for the claim in respect of the balance due under Interim Valuation No 10. However, he submitted that the adjudicator did not fail to address the counterclaim but simply regarded it as a defence that was bound to fail in the absence of a withholding notice. If this was an error, then he submits that it was an error made by the adjudicator when addressing the right question, namely whether or not the counterclaim could be deployed as a defence to Urang's claims in the adjudication."
"30. I have already set out in paragraphs 49 and 50 of the Decision in which he concluded that in the absence of a withholding notice he was "unable to assess the value" of Century's counterclaim.
31. Mr Khan submits that in adopting this approach the adjudicator wrongly failed to deal with an issue that was before him, namely to consider the counterclaim. In my judgment, this is not a correct submission. The question for the adjudicator was whether, and if so to what extent, Century's counterclaim could be deployed as a defence to Urang's claims in the adjudication. If the adjudicator concluded, as he did, that the counterclaim could not be deployed as a defence to the claims in the absence of a valid withholding notice, then he answered the question. The fact that he answered it wrongly affords Century no defence."
The Consequences flowing from the preceding Conclusions.