![]() |
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | |
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> John Sisk and Son Ltd v Capital & Centric (Rose) Ltd [2025] EWHC 594 (TCC) (14 March 2025) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2025/594.html Cite as: [2025] EWHC 594 (TCC) |
[New search] [Printable PDF version] [Help]
BUSINESS & PROPERTY COURTS IN MANCHESTER
TECHNOLOGY AND CONSTRUCTION COURT (KBD)
1 Bridge Street West, Manchester M60 9DJ |
||
B e f o r e :
SITTING AS A JUDGE OF THE HIGH COURT
____________________
JOHN SISK AND SON LIMITED |
Claimant |
|
- and - |
||
CAPITAL & CENTRIC (ROSE) LIMITED |
Defendant |
____________________
Abdul Jinadu (instructed by Excello Law Limited, Solicitors, Manchester) for the Defendant
Hearing dates: 16-17 December 2024
Draft judgment circulated: 6 March 2025
____________________
Crown Copyright ©
Remote hand-down
This judgment was handed down remotely at 10:00am on 14 March 2025 by circulation to the parties or their representatives by email and by release to The National Archives.
His Honour Judge Stephen Davies:
Sect | Paras | |
A | Introduction and summary of decision | 1 - 8 |
B | The key relevant clauses of the design and build contract | 9 - 45 |
C | Sisk's pleaded case and the competing arguments | 46 - 58 |
D | The relevant principles of contract interpretation | 59 - 64 |
E | Should I have regard to the pre-contractual negotiations and, if so, on what basis and for what purpose(s)? | 65 - 74 |
F | My decision as a matter of construction of the contract documents alone | 75-120 |
G | Would my decision have been different if I had had regard to the pre-contractual negotiations? | 121-135 |
H | The appropriate declaratory relief | 136 - 137 |
I | Postscript breach of the confidentiality restriction in the draft judgment | 138 - 143 |
A. Introduction and summary of decision
B. The key relevant clauses of the design and build contract
B(i). The contract format
Sisk Clarification | Comments / Risk Owner | |
2 | Existing Structures Risk including ability to support / facilitate proposed works | The Employer is to insure the Existing buildings/ works. Employer also to obtain warranty from Arup with regard to the suitability of the proposed works. Employer Risk |
B(ii) relevant contractual provisions relating to consultants
B(iii) relevant contractual insuring provisions
C. Sisk's pleaded case and the competing arguments
a. Under the contract the risk of additional cost or delay being incurred as a result of the state of the existing structures, including their being unable to support or facilitate the proposed works, lies with C&C.
b. It is entitled to an extension of time and additional money in the event that additional cost or delay is incurred as a result of the state of the existing structures, including their being unable to support or facilitate the proposed works.
D. The relevant principles of contract interpretation
"Evidence of pre-contractual negotiations is not generally admissible to interpret the concluded written agreement. But evidence of pre-contractual negotiations is admissible to establish that a fact was known to both parties; to determine which party put forward a particular term[7]; and to elucidate the general object of the contract. Evidence that parties negotiated on the basis of an agreed meaning is only admissible in support of a claim of estoppel or rectification."
" What is not permissible, as the decision of the House of Lords in the Chartbrook case confirms, is to seek to rely on evidence of what was said during the course of pre-contractual negotiations for the purpose of drawing inferences about what the contract should be understood to mean. It is also clear from the Chartbrook case that it is not only statements reflecting one party's intentions or aspirations which are excluded for this purpose but also communications which are capable of showing that the parties reached a consensus on a particular point or used words in an agreed sense. The exclusion of such evidence was justified in the Chartbrook case, not on the ground that it will always or necessarily be irrelevant, but because of the costs and other practical disadvantages that would result from relaxing the rule and because the "safety devices" of rectification and estoppel will generally prevent the exclusionary rule from causing injustice."
E. Should I have regard to the pre-contractual negotiations and, if so, on what basis and for what purpose(s)?
F. My decision as a matter of construction of the contract documents alone
F(i) The contract clarifications document
F(ii) The tender submission clarifications document
G. Would my decision have been different if I had had regard to the pre-contractual negotiations?
H. The appropriate declaratory relief
I. Postscript breach of the confidentiality embargo in the draft judgment
Note 1 The design and construction of two new residential buildings, repairs and refurbishment of two listed mills and two further existing buildings together with external works and other associated works. [Back] Note 2 It appears that two issues were referred to the adjudicator, first ground conditions and second existing structures, but these proceedings are only concerned with the latter. [Back] Note 3 Referred to in the contract documents as a pendrive. [Back] Note 4 Cinns was C&Cs project representative and Employers Agent under the design and build contract. [Back] Note 5 This is usually an abbreviation for Pre-Construction Services Agreement and, in this context, is plainly a reference to the period of time preceding the entry into the design and build contract in which Sisk was at least in C&Cs opinion in a position to investigate and satisfy itself as to such matters. [Back] Note 6 I have not been addressed on this, and there is an exclusion at clause 6.8(b) which might be engaged. [Back] Note 7 This is only admissible where the contra proferentem principle is in play: Lewison at 3.55. [Back] Note 8 It may be said that this would have presented a logistical difficulty, in that it might have needed to have been printed out in landscape to capture all of its content. It is also unknown whether, if that had been done, it would have included column F or whether that would have been hidden, as it was in the electronic version. [Back] Note 9 C&Cs primary position is that it is clear and means what it says. [Back]