STATUTORY INSTRUMENTS


2001 No. 4011

ELECTRICITY

GAS

The Electricity and Gas (Energy Efficiency Obligations) Order 2001

Approved by both Houses of Parliament

  Made 14th December 2001 
  Coming into force 15th December 2001 

The Secretary of State for Environment, Food and Rural Affairs[1], in exercise of the powers conferred upon her by section 33BC(1) of the Gas Act 1986[2], section 41A of the Electricity Act 1989[3] and section 103(1) of the Utilities Act 2000[4], having consulted the Gas and Electricity Markets Authority, the Gas and Electricity Consumer Council, gas transporters, gas suppliers, electricity distributors and electricity suppliers, and other persons with whom she considered consultation to be appropriate[5], and having had regard to the matters specified in section 33BC(4) of the Gas Act 1986 and section 41A(4) of the Electricity Act 1989, hereby makes the following Order, of which a draft has been laid before, and approved by Resolution of, each House of Parliament:

Citation, commencement, and interpretation
     1.  - (1) This Order may be cited as the Electricity and Gas (Energy Efficiency Obligations) Order 2001 and shall come into force on the day after that on which it is made.

    (2) In this Order - 

expressed in tonnes of carbon per year;

and where electricity or gas is supplied to a consumer, or proposed to be supplied to a future consumer, both at domestic premises and at premises that are not domestic premises, means the consumer or future consumer in relation only to the domestic premises;

means the energy efficiency target having effect for the time being as regards that period;

    (3) For the purposes of this Order, the promotion of the supply to premises of - 

shall be treated as promoting energy efficiency.

Energy efficiency obligations
     2.  - (1) On 1st April 2002 each supplier to which this paragraph applies shall be subject to the obligation to achieve, within the period of three years beginning on that date, and in accordance with this Order, the target determined for it by the Authority[7] under article 3(2).

    (2) Paragraph (1) applies to - 

which, on 31st December 2001, supplies at least 15,000 domestic consumers.

    (3) Where a person - 

its obligation under that paragraph applies separately in relation to its functions as an electricity supplier and as a gas supplier.

    (4) If a supplier of electricity or gas to which paragraph (1) does not apply supplies at least 15,000 domestic consumers on 31st December 2002 it shall, with effect from 1st April 2003, be subject to the obligation to achieve, within the period beginning on 1st April 2003 and ending immediately before 1st April 2005, and in accordance with this Order, the target determined for it by the Authority under article 3(4).

    (5) If a supplier of electricity or gas to which neither paragraph (1) nor paragraph (4) applies supplies at least 15,000 domestic consumers on 31st December 2003, it shall, with effect from 1st April 2004, be subject to the obligation to achieve, within the period beginning on 1st April 2004 and ending immediately before 1st April 2005, and in accordance with this Order, the target determined for it by the Authority under article 3(4).

    (6) For the purpose of ascertaining, under this article or under article 3(6), the number of domestic consumers supplied, any consumers - 

shall be treated as supplied by the supplier.

    (7) In paragraph (6) "holding company" and "subsidiary" have the same meaning as in section 736 of the Companies Act 1985[8].

Determination and notification of energy efficiency targets
     3.  - (1) For the purposes of the exercise by the Authority of its functions under this Order, the overall target for the promotion of improvements in energy efficiency in Great Britain, as regards the period beginning on 1st April 2002 and ending immediately before 1st April 2005, is 62 fuel-standardised terawatt hours.

    (2) The Authority shall - 

    (3) The criteria mentioned in paragraph (2) are - 

    (4) The target to be determined for each supplier to which article 2(4) or (5) applies shall be ascertained, subject to subsection (4) requirements, by - 

    (5) The Authority shall, by notice in writing given to each supplier to which article 2(4) or (5) applies, inform the supplier of the target determined for it in accordance with paragraph (4) above; and the notice shall be given - 

    (6) Each supplier for which a target is to be determined in accordance with paragraph (2) or (4), shall, not later than 10th January preceding each year beginning 1st April in which it is subject to an obligation under article 2, notify the Authority in writing of the number of its domestic consumers on the preceding 31st December.

    (7) For the purposes of this article "relevant adjustment factor" means the percentage shown as applicable to the supplier in question by reference to the number or, as the case may be, the assumed number, of its domestic consumers on 31st December 2001, by reference to graph 1 and, in the case of a supplier of up to 1 million domestic consumers, more particularly by reference to graph 2, set out in Schedule 1 to this Order.

Alteration of energy efficiency targets
    
4.  - (1) Where the number of domestic consumers supplied on 31st December 2002 by a supplier to which paragraph (1) of article 2 applies, differs from the average of - 

the Authority shall, so far as consistent with subsection (4) requirements, alter the supplier's target for the period beginning on 1st April 2002 and ending immediately before 1st April 2005.

    (2) Where the number of domestic consumers supplied on 31st December 2003 by a supplier to which paragraph (1) or (4) of article 2 applies, differs from the average of - 

the Authority shall, so far as consistent with subsection (4) requirements, alter the supplier's target for the period beginning on 1st April 2002 or, in the case of a supplier to which paragraph (4) of article 2 applies, 1st April 2003 and ending immediately before 1st April 2005.

    (3) The criteria by reference to which the Authority shall determine the extent to which a supplier's target is altered under paragraph (1) or (2) shall include the number by which - 

    (4) Where at any time before 31st December 2003, a supplier to which paragraph (1) or (4) of article 2 applies ceases to supply at least 15,000 domestic consumers, it shall forthwith give to the Authority notice in writing to that effect.

    (5) Where, at any time before 31st December 2003, a supplier which has given notice under paragraph (4) again becomes the electricity supplier or the gas supplier of more than 15,000 domestic consumers, it shall forthwith give to the Authority notice in writing to that effect.

    (6) Where the Authority agrees to any matter referred to in paragraph (1) of article 11, it shall make an appropriate alteration to the target of the supplier or suppliers concerned.

    (7) Where the Authority alters the target of a supplier pursuant to any of paragraphs (1), (2) or (6), the Authority shall, by notice in writing to the supplier, inform it of its target as so altered.

Additional sources of energy
    
5. In the application, for any purpose of this Order, of the definition of "energy efficiency target" in section 33BC(2) of the 1986 Act or section 41A(2) of the 1989 Act, efficiency in the use by consumers of coal, liquid petroleum gas or oil shall also be regarded as energy efficiency[9].

Qualifying action
     6.  - (1) Subject to paragraph (2), activity (of any description) that produces, or may reasonably be expected to produce, an improvement in energy efficiency is qualifying action.

    (2) Activity is not to be regarded as qualifying action unless the supplier by which it is undertaken secures that at least 50 per cent of the energy savings attributable to its total activity is achieved in relation to domestic consumers who are in receipt of at least one of the benefits described in Schedule 2 to this Order.

Provision of information by suppliers
    
7.  - (1) The Authority may, by notice in writing, require a supplier which is for the time being subject to an energy efficiency obligation under this Order to give to the Authority, within such period as may be specified in the notice, such information as to the steps to be taken by the supplier to comply with its obligation as the Authority may reasonably require.

    (2) Without prejudice to the generality of paragraph (1), the Authority may require the provision of information as to - 

Determinations by the Authority
    
8.  - (1) The Authority shall determine, with respect to each supplier by which information is provided in accordance with article 7 - 

    (2) Where a supplier provides information as to its proposals for undertaking energy service action, the Authority shall, subject to paragraph (3), for the purposes of paragraph (1)(b) attribute to the qualifying action comprised in that energy service action an improvement in energy efficiency that exceeds by 50 per cent the improvement that may reasonably be expected to be achieved.

    (3) The Authority may not make the attribution referred to in paragraph (2) as regards more than 10 per cent of the supplier's target.

    (4) The Authority shall give written notice to the supplier of the matters determined under paragraph (1) as soon as reasonably practicable after receipt of information from the supplier under article 7.

    (5) For the purposes of this Order, determinations of which notice is given before 1st April 2002 shall be as effective as those of which notice is given on or after that date.

Effect of change of supplier
    
9. Where a domestic consumer in relation to whom qualifying action has been completed, or has been begun, ceases to take his supply from the supplier by whom the action was initiated, the improvements in energy efficiency attributable to that action shall accrue to that supplier; but where the consumer becomes a domestic consumer of another supplier before the completion of the qualifying action, the improvements shall accrue to each supplier in the same proportion as the action taken by each of them bears to the totality of the qualifying action.

Information as to compliance
    
10.  - (1) The Authority may, by notice in writing, require a supplier which is at any time between 1 April 2002 and 31 March 2005 subject to an energy efficiency obligation under this Order to give to the Authority, within such period as may be specified in the notice, such information as to the steps taken by the supplier to comply with its obligation as the Authority may reasonably require.

    (2) Without prejudice to the generality of paragraph (1), the Authority may require the provision of information as to - 

Energy efficiency targets: further provision
    
11.  - (1) A supplier which is for the time being subject to an energy efficiency obligation ("the first supplier") may, with the written agreement of the Authority - 

    (2) Action taken by a supplier before 1st April 2002 may not be treated as mentioned in paragraph (1)(c) if action of that description has already been so treated and accounts, in aggregate, for more than 10 per cent of the supplier's target.

    (3) The Authority shall, in relation to any such agreement as is referred to in paragraph (1), make a record - 

    (4) As soon as reasonably practicable after the making of a record under paragraph (3), the Authority shall provide a copy of it - 

    (5) A record made by the Authority under paragraph (3) may be kept in any form and shall be kept for a period of not less than 5 years from the date on which it was compiled.

Enforcement of energy efficiency obligations
    
12.  - (1) The requirement imposed on a supplier under paragraph (1), (4) or (5) of article 2 to achieve its energy efficiency obligation shall be treated as a relevant requirement - 

    (2) In determining whether a supplier has failed to comply with relevant requirements, regard shall be had, in particular - 

relevant to the period in question for the purposes of Part II of the 1986 Act or Part II of the 1989 Act or, as the case may be, both of those purposes.

Information for the Secretary of State
    
13. The Authority shall, not later than 31st July in each of the years 2003, 2004 and 2005, submit to the Secretary of State a report for the period of 12 months ending on the preceding 31st March; and the report shall contain, as regards each supplier which, in any part of the period to which the report relates, was subject to an energy efficiency obligation under this Order, particulars of - 



Signed by authority of the Secretary of State for Environment, Food and Rural Affairs


Michael Meacher
Minister of State, Department for Environment, Food and Rural Affairs

14th December 2001



SCHEDULE 1
article 3(7)


RELEVANT ADJUSTMENT FACTOR






SCHEDULE 2
article 6(2)


BENEFITS RELEVANT TO QUALIFYING ACTION


     1. In this Schedule - 

     2. The benefits relevant for the purposes of articles 6 and 10 are - 



EXPLANATORY NOTE

(This note is not part of the Order)


Article 2(1) of this Order imposes on each electricity and gas supplier which, on 31st December 2001, supplies in any part of Great Britain at least 15,000 domestic consumers, an obligation to achieve improvements in energy efficiency over the period beginning on 1st April 2002 and ending immediately before 1st April 2005. Article 2(4) makes corresponding provision for those suppliers whose domestic consumers in Great Britain are fewer than 15,000 on 31st December 2001 but are at least 15,000 on 31st December 2002. Article 2(5) makes corresponding provision for those suppliers whose domestic consumers in Great Britain are fewer than 15,000 both on 31st December 2001 and on 31st December 2002, but are at least 15,000 on 31st December 2003.

Article 3 requires the Gas and Electricity Markets Authority ("the Authority") to determine the target of individual electricity and gas suppliers with a view to achieving an overall improvement in energy efficiency in Great Britain of 62 fuel-standardised terawatt hours during the period beginning on 1st April 2002 and ending immediately before 1st April 2005. (A terawatt hour is equivalent to 1,000 million kilowatt hours.) Article 3(7) introduces the graphs in Schedule1, which have effect for the purpose of applying the "relevant adjustment factor" in the calculation of a supplier's target.

Article 4 requires the Authority to alter a supplier's target to reflect certain changes in the number of the supplier's domestic consumers.

Article 5 provides that efficiency in the use by consumers of coal, liquid petroleum gas or oil is to be regarded as energy efficiency for the purposes of the term "energy efficiency target" used in section 33BC of the Gas Act 1986 and section 41A of the Electricity Act 1989. (By virtue of subsection (2) of those sections, efficiency in the use by consumers of electricity, and of gas conveyed through pipes, is energy efficiency for the purposes of those sections.)

Article 6(1) provides that any improvement in energy efficiency is qualifying action contributing to the satisfaction of a supplier's target; but this is qualified by article 6(2) which requires the supplier to secure that at least 50 per cent of the energy savings attributable to the activity that it carries on with a view to complying with its target is achieved in relation to domestic consumers who are in receipt of at least one of the benefits in Schedule 2 to the Order.

Article 7 enables the Authority to require information from suppliers as to the steps to be taken by them to comply with their obligations under the Order.

Article 8 requires the Authority to make determinations as to whether particular action that a supplier intends to take will qualify for the purpose of achieving the whole or any part of its energy efficiency target. Special provision is made in article 8(2) and (3) in relation to "energy service action", as defined in article 1(2) of the Order.

Article 9 makes provision for the case where a domestic consumer changes his supplier.

Article 10 enables the Authority to obtain information from suppliers about the steps that they have taken towards satisfaction of their targets.

Article 11 allows suppliers, with the Authority's agreement, to "trade" qualifying action, to transfer the whole or part of their target, and to treat action taken before 1st April 2002 as contributing to the achievement of their target under the Order. In the latter case, article 11(3) imposes the restriction that not more than 10 per cent of the supplier's target can be met by action taken before 1st April 2002.

Article 12 makes provision for enforcement.

Article 13 requires the Authority to make annual reports to the Secretary of State on the progress made by suppliers in meeting their targets under the Order.

A Regulatory Impact Assessment has been prepared for this Order and placed in the Library of each House of Parliament. Copies of the Assessment can be obtained from Sustainable Energy Policy Division of the Department for Environment, Food and Rural Affairs at Zone 6/G15, Ashdown House, 123 Victoria Street, London SW1E 6DE.


Notes:

[1] The functions to which this Order relates were entrusted to the Secretary of State for the Environment, Transport and the Regions immediately before 7th June 2001 and were entrusted to the Secretary of State for Environment, Food and Rural Affairs before the making of the Secretaries of State for Transport, Local Government and the Regions and for Environment Food and Rural Affairs Order 2001 (S.I. 2001/2568). See, in particular, article 12 of that Order (supplementary provision for continuity).back

[2] 1986 c. 44. Section 33BC was substituted for section 33BB by the Utilities Act 2000 (c. 27), section 99.back

[3] 1989 c. 29. Section 41A was substituted for section 41 by the Utilities Act 2000, section 70.back

[4] 2000 c. 27.back

[5] See section 33BC(11) of the Gas Act 1986, section 41A(11) of the Electricity Act 1989, and section 103(4) of the Utilities Act 2000.back

[6] Published by the Department of the Environment, Transport and the Regions, March 2001. Copies may be obtained from PO Box 236, Wetherby, West Yorkshire, LS23 7NB (Tel: 0870 126 236) or downloaded from www.defra.gov.uk/environment/envrp/gas/index.html.back

[7] I.e. the Gas and Electricity Markets Authority; see section 66(1) of the 1986 Act which was amended by the Utilities Act 2000 (c. 27), section 108 and Schedule 6 Part II, paragraphs 1 and 22; and section 111(1) of the 1989 Act, which was amended by the Utilities Act 2000, section 108 and Schedule 6 Part II, paragraphs 24 and 40.back

[8] 1985 c. 6. Sections 736 and 736A were substituted for the original section 736 by section 144(1) of the Companies Act 1989 (c. 40).back

[9] By virtue of section 33BC(2) of the 1986 Act and section 41A(2) of the 1989 Act, efficiency in the use by consumers of electricity, and of gas conveyed through pipes, is energy efficiency for the purposes of energy efficiency targets within the meaning of those sections.back

[10] 1992 c. 4.back

[11] S.I. 1983/883; amendments relevant to this Order are noted below.back

[12] See section 5 of the Industrial Injuries and Diseases (Old Cases) Act 1975 (c. 16) which was repealed, with savings, by the Social Security (Consequential Provisions) Act 1992 (c. 6).back

[13] Council tax benefit, housing benefit and income support are provided for in Part VII (income-related benefits) of the Social Security (Consequential Provisions) Act 1992 (c. 6).back

[14] 1995 c. 18. For the definition of "an income-based jobseeker's allowance", see section 1(4).back

[15] Provided for in Part VII of the Social Security Contributions and Benefits Act 1992, as amended by the Tax Credits Act 1999 (c. 10).back

[16] 1992 c. 5.back

[17] Article 10 was amended by S.I. 1993/598 and 1996/1638.back

[18] 7 & 8 Geo.5 c. 51.back

[19] Article 26A was inserted by S.I. 1983/116 and amended by S.I. 1983/1521, 1986/592, 1990/1308, 1991/766, 1992/710, 1995/766, 1997/766 and 2001/409.back

[20] Article 25A was inserted by S.I. 1983/1164 and amended by S.I. 1983/1540, 1986/628, 1900/1300, 1991/708, 1992/702 and 1995/455.back



ISBN 0 11 039040 7