[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Aqua Leisure International Ltd v Benchmark Leisurel Ltd [2020] EWHC 3511 (TCC) (18 December 2020) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2020/3511.html Cite as: [2020] EWHC 3511 (TCC) |
[New search] [Printable PDF version] [Help]
QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
AQUA LEISURE INTERNATIONAL LIMITED |
Claimant |
|
- and – |
||
BENCHMARK LEISURE LIMITED |
Defendant |
____________________
Mr James Bowling (instructed by The Endeavour Partnership) for the Defendant
Hearing dates: 1 December 2020
____________________
Crown Copyright ©
"Covid-19 Protocol: This judgment was handed down by the judge remotely by circulation to the parties' representatives by email and release to Bailii. The date and time for hand-down is deemed to be Friday 18th December 2020 at 10:30am"
His Honour Judge Bird :
"it is perfectly obvious that the evidence before the Court now is unlikely to be the end of matters….[t]here are almost certainly bound to be further witnesses, documents and conversations in relation to those events that go to whether or not the STC rubric was waived by conduct. The court should have regard to the likelihood of such evidence becoming available before trial".
"the judge knew that the totality of the evidence that the parties would wish to bring before the court was unlikely to be contained in the witness statements. Thus he knew that he was deciding what Mr Bartlett termed a "no case to answer submission" without deciding whether any further agreement between the experts would be forthcoming and, if so, whether it would be admitted and if so, whether it would support Brompton's case".
"it must substantiate that assertion by describing, at least in general terms, the nature of the evidence, its source and its relevance to the issues before the court. The court may then be able to see that there is some substance in the point and that the party in question is not simply playing for time in the hope that something will turn up"
Background
i) £143,411.13 plus VAT[1] in respect of the principal claim
ii) interest on that sum at the contractual rate in the total sum of £5,374.18 (with an accruing daily rate of £22.04)
iii) £12,500 in respect of legal costs under section 5A of the Late Payment of Commercial Debts (Interest) Act 1998 and the fixed fee of £100 under the Act and
iv) his fees of £10,470.
i) £49,067.50 plus VAT was to be paid on 4 September 2017. This sum was paid on 9 September 2017.
ii) £29,381.96 plus VAT was to be paid on or before 15 October 2017, but before warranty works commenced. That sum was paid in 2 instalments by 22 November 2017. On receipt warranty works were commenced.
iii) £29,548.55 plus VAT was to be paid on completion of the warranty works. An invoice was issued in that sum on 1 April 2018. That sum was paid in 3 instalments, the last payment was made on 29 August 2018.
iv) £110,000 plus VAT was to be paid on or before 22 August 2018 to be underwritten by Abbey. This sum has not been paid.
The Claim for all sums save those awarded under the 1998 Act
The arguments
The Law
i) Paragraph 47:
"…in a case where a contract is being negotiated subject to contract and work begins before the formal contract is executed, it cannot be said that there will always or even usually be a contract on the terms that were agreed subject to contract. That would be too simplistic and dogmatic an approach. The court should not impose binding contracts on the parties which they have not reached. All will depend upon the circumstances."
ii) Paragraph 56 (having set out at para.55 that a contact negotiated subject to contract may become a binding contract "if the parties later agree to waive that condition"):
"Whether [in a without prejudice subject to contract case] the parties agreed to enter into a binding contract, waiving reliance on the "subject to [written] contract" term or understanding will again depend upon all the circumstances of the case, although the cases show that the court will not lightly so hold."
Discussion
"that (a) neither party intends to be bound either in law or in equity unless and until a formal contract is made; and (b) that each party reserves the right to withdraw until such time as a binding contract is made. It follows, therefore, that in negotiating on that basis both [parties] took the commercial risk that one or other of them might back out of the proposed transaction…. In short, a "subject to contract" agreement is no agreement at all."
i) Both parties saw the reduction to writing of an agreement as a mere formality and always intended that the payment resolution agreement would be acted upon
ii) The claimant gave the defendant credit for payments made under the agreement when the deed of settlement was prepared so that such payments were "unambiguously banked"
iii) Even when the deed was not signed the claimant demanded compliance with the agreement, making express reference to it as an agreement. This was only consistent with the agreement being binding. This is in reference to the payment of £9,548 plus VAT as the final instalment of the payment of £29,548.55 plus VAT agreed to be paid by 1 April 2018 but in fact not paid until August 2018.
iv) Performance of the warranty works itself is good evidence that the agreement was seen as binding.
i) The agreement expressed to be "subject to contract" and "without prejudice" was intended to represent a compromise of issues that had arisen in the execution of the 2015 contract.
ii) In the absence of a compromise, sums were still due under the 2015 contract and under the terms of the binding adjudication award. It is impossible to conclude that the payment and acceptance of sums of money already due under those primary obligations points to the existence of a new contract of compromise.
iii) The fact that works were carried out is in my judgment equally incapable of supporting the argument that a new contract was arrived at.
iv) The fact that monies were paid and "banked" is not evidence that there was a new contract. It is simply evidence that the parties were working together to try to settle debts that had arisen under the primary obligations, get work done and move forward.
v) Again, the fact that money was paid after it became clear that there would be no reduction of terms into writing does not indicate a new contract was entered into. The timing of the payment or payments is not in my view of central relevance.
vi) All indicators (not least demands for the agreement to be signed after a draft had been provided) strongly point to the conclusion that the claimant wanted the original compromise agreement (albeit on slightly different terms) to be finalised. The impartial observer would conclude without reservation that the claimant had no desire to enter into a new contract.
vii) This case is a paradigm example of why the court "will not lightly hold" that a condition that negotiations and agreements are "subject to contract" has been superseded. The parties set their own rules of engagement. They agreed that there would be no binding contract until the terms were reduced to writing and signed off. They clearly envisaged that an agreement would be reached but that it would not be enforceable until the formalities had been observed. The presence of an agreement that was acted on, is not therefore without more enough to indicate that the parties intended to be bound. It was obvious that the agreement would be acted upon before it became binding. Payments would be made and work would be done. Once "banked" those sums would on any view need to be accounted for regardless of whether there was a binding contract. Everything that happened during the course of the parties' dealings with one another happened at a time when the ground rules applied.
Sums awarded under the 1998 Act
"A waiver can be said to arise where a party, who knows or should have known of grounds for a jurisdictional objection, participates in the adjudication without any reservation of any sort; its conduct will be such as to demonstrate that its non-objection on jurisdictional grounds and its active participation was intended to be and was relied upon by the other party (and indeed the adjudicator) in proceeding with the adjudication. It would be difficult to say that there was a waiver if the grounds for objection on a jurisdictional basis were not known of or capable of being discovered by that party."(emphasis added)
i) The absence of jurisdiction in the present case (the term "power" is equally apt: see paragraphs 44 and 54 of Enviroflow) does not arise out of a mere procedural failure (which could be waived) but rather out of an express statutory provision removing the right to rely on the 1998 Act (as explained in Enviroflow).
ii) Where statute prevents reliance on the 1998 Act the parties cannot simply override the effect of the statute by agreement or still less by conduct.
iii) The statutory removal of the right to rely on the 1998 Act in these circumstances means that the claimant cannot reasonably be taken to have relied on the defendant's failure to raise the point as a waiver of the right ever to do so.
iv) Waiver in the sense used here is a type of estoppel, where the conduct of one party sends a clear and unambiguous signal to the other that he intends to act in a certain way and it would be unconscionable for him then to act contrary to that signal. Although the point was not argued, it seems to me to be clear that as a matter of law, an estoppel (and so the waiver) cannot operate.
v) I take comfort from the fact that the question of waiver was not raised in Enviroflow itself either by the parties or by the Judge. There (see paragraph 42) the right to costs under the 1998 Act was raised in the Notice of Adjudication and disputed.
Note 1 The claim was for £160,077.80 net of VAT. Credit was given for £16,666.67 (the payment of £20,000 net of VAT). This leaves a balance due of £143,411.13 net of VAT. [Back]